CLP had been planning this project for some
time and had anticipated to the use of at least two rigs to
speed the process along.
Once the work started however it was apparent, due to the fact
we now use one of our mid-sized drilling rigs on these shallower
type gas wells, that one rig was easily capable of keeping the
project on schedule.
Site:
Beddingham Landfill Site
Client:
Viridor Waste Management
Date:
September 2006
Scope
Remediate 4 existing
leachate chambers to 50m depth
Viridor needed to remediate some as built
leachate chambers on their Beddingham Landfill site but were
uncomfortable retro drilling new wells near to the basal liner
on such a sensitive site.
It was decided to drive specially designed steel casings through
the existing chambers using a vibrating percussive technique
similar to those used in sheet piling.
All four wells were remediated to their original depth without
risking a breach of the basal liner.
Site:
Trecatti Landfill Site
Client:
Biffa Waste Services
Date:
Summer
2006
Scope
To drill 3 Groundwater
Monitoring Boreholes to depths in excess of 230m below
ground level
Biffa required 3 monitoring boreholes to be
drilled around their Trecatti Landfill site. A site known for
it’s exposure to extreme weather conditions and a reputation for
awkward drilling due to the extensive mine workings in the area.
The job proved none too straight forward and had to be suspended
at one point for extra equipment to be manufactured as our
original proposed technique wasn’t too successful.
However, everyone involved stuck to the task and the wells were
completed successfully before the Autumnal weather could hamper
progress further.
Site:
Enderby Warren Closed
Landfill Site
Client:
SITA (UK) Ltd
Date:
Nov
2005
Scope
To drill to base of landfill
site estimated in the region of 70-80m bgl. To install
double steel casing to base of landfill.
Utilising one of Magpie’s three MC3000
drilling rigs, the well was drilled with 450mm barrel auger to
50m, where upon a 406mm plain threaded steel casing was
installed. The well was advanced with 350mm barrel auger until
basal drainage rock was encountered at the base of the landfill.
Depth achieved 74.50m. The secondary 273mm well casing was
installed to 74m. Due to the success of the first well, the
exercise was repeated and a second identical well drilled and
installed. The wells were drilled in two separate phases with a
total time on site of three weeks.
Site:
Bubbenhall Landfill Site
Client:
Waste Recycling Group (WRG)
Date:
October
2005
Scope
Cell Base Investigation
WRG were required to install 6 leachate
extraction wells to the base of the site at Bubbenhall Landfill.
Prior to drilling it was imperative they obtained investigative
information as to the base levels. On previously projects they
had utilised bespoke Cone Penetration Test (CPT) machines to
ascertain the base levels, however these had limited depth
capabilities and still required a subsequent mobilisation of a
drilling rig to complete the work once the depth was known.
To enable WRG to undertake the drilling as well as the
investigation we used a sampling probe system which had been
developed to find basal drainage layers without piercing
membranes. The drilling was carried out to a designated depth
then ceased at a “safe” level above the liner. The probing tool
was then installed into the drilled well and probed the waste
material in 200-300mm increments, whilst taking samples of
materials. Once the base layer was intercepted, drilling could
continue to the levels ascertained by the probe.
Not only did this ensure safe drilling practice avoiding any
damage to the base liner, but also had very small financial
implications for the client.
Site:
Poplars Landfill Site
Client:
Biffa Waste Services
Date:
September 2005
Scope
Deep Leachate Extraction
Wells
We were approached by Biffa to drill 600mm
diameter leachate extraction wells to various depths up to 48m.
Whilst we would normally advise our clients against attempting
these depths at such large diameters, Biffa had already
purchased the well liner materials for another drilling
contractor who had failed to install the wells.
Biffa were aware of our recently purchased MC3000 rigs with
600mm diameter capacity and requested we attempt the scope they
required with one of these drilling rigs. We agreed and the
project was completed, with 11 leachate extraction wells
successfully installed to the sites compliance levels.
Site:
Packington Landfill Site
Client:
SITA (UK) Ltd
Date:
Three
phases, commencing September 2005
Scope
To drill over 50 leachate
extraction wells within SITA UK’s flagship site at
Little Packington. Depths ranging from 10 -60m bgl, with
250mm/315mm HDPE installations.
With as many as three of Magpie’s rigs on
this substantial project, drilling was undertaken using 450mm
barrel augers for the installation of 250mm HDPE butt fused
welded well liners, incorporating a 315mm perforated telescopic
“boot” at the base. The majority of the wells were drilled
successfully despite some very difficult drilling conditions. In
areas where excessive collapsing was encountered, the client
requested the installation of 406mm steel casings to support the
wells, to allow for the placement of the permanent HDPE liner.
Site:
Pitsea Landfill Site
Client:
Cleanaway
Date:
November 2001
Scope
640 Gas Extraction Wells
In late 2001 Magpie Drilling was still a
relatively small firm but already starting to build a good
reputation for quality and reliability. We were approached by
Cleanaway to participate in what was by any scale a massive
drilling project.
Cleanaway had an agreement in place with the Environment Agency
that the gas control system incorporating the gas wells would be
operational by April 2002. We were recommended to them as a
highly dependable drilling contractor specialising in landfill
drilling activities.
The work was completed ahead of schedule in March 2002, despite
the scope being increased to 690 wells. Since this project
Magpie Drilling has become the principal landfill drilling
contractor for Cleanaway.